Your previous page
You are here: Home
> Key reports > Directors'
report > 6. Research development and demonstration
2006 |
2005 |
2004 |
|
(12 months) |
(15 months) |
(12 months) |
|
| Research, development and demonstration, Rm | 167,1 |
227,6 |
188,9 |
| PBMR, Rm | 6,9 |
35,0 |
35,0 |
| Total, Rm | 174,0 |
262,6 |
223,9 |
| Percentage of revenue, % | 0,49 |
0,63 |
0,66 |
| Underground coal gasification is a process in which coal is converted on site into a combustible gas that can be used for power generation or chemical production. This avoids the need for coal mining, transportation, preparation, the gasification process, and the transportation and disposal of ash. This has cost, labour and environmental benefits. The technology has been researched over the past 50 years, and has been in commercial operation for more than 40 years in the former Soviet Union. The gas was used for heating and power generation. Although this technology is strictly commercially mature, former Soviet technology is only now emerging in the western world with the first pilot plant installed and operating for four years in Australia. There have been many national research and development programmes on underground coal gasification running in the USA, UK, Belgium, New Zealand and, more recently, Spain, operating with the more expensive and non-commercial USA technology. The Chinese have developed another variant, designed specifically to extract remaining coal reserves from previously worked underground coal mines. |
Knowledge management
Evaluation of an appropriate platform for the optimisation and delivery of knowledge in the organisation was undertaken. Effective solutions were identified for knowledge retention.Eskom power series
The Eskom power series of technical books is being developed to capture technical skills from experienced engineers and specialists and making this available to young graduates.
Climate change and rainfall
In 2004, an attempt was made to model possible climatic change projections over a specific region of South Africa to aid planning for water resources and power utility expansion. In 2005, a study was undertaken to determine whether any significant observed trends appear in South African rainfall measured over the past 42 years (1960 to 2001), and whether this was due to climate change. It appeared as if there is a seasonal shift in rainfall towards drier conditions in the early winter over the central summer rainfall region, and wetter conditions in the late winter and early summer over the western coastline and interior. The research did not link the changes in rainfall to climate change.Coal Clinker productionEskom annually produces over 30 million tons of coal ash. A study has proven that it is possible to produce cement clinker from coal ash. This process of recycling ash will have positive economic and environmental benefits.
This project was aimed at improving emission factors in the power generation
sector of southern Africa. Emission factors specific to the region were
generated through fuel and power plant analysis. The findings include
some deviation of emission factors from the intergovernmental panel
on climate change default values. The project also generated useful
information for improving national greenhouse gas inventories and emission
baselines.
|
Eskom will proceed with the next engineering phase of the project. This phase will concentrate on risk reduction efforts and updating the business case for the proposed pilot plant. Discussions with technology partners have been initiated and a draft project plan completed.
Ocean energy
Eskom is investigating the feasibility of ocean energy as a future primary
energy source. Current research is monitoring and evaluating various international
initiatives. Once these studies have been completed, Eskom will assess the
feasibility of different technologies for applicability under South African
conditions.
Fuel cell
Eskom and the University of the Western Cape have collaborated on fuel cell research for the past three years. This research was mainly for the development of skills in this field. The primary objective of the project is to develop potentially commercial components for direct methanol fuel cells. A variety of commercial and internally produced proton conductive membranes, catalyst and membrane electrode assemblies were produced. Production methods were improved to gain maximum power output from the direct methanol fuel cell.
Nuclear
Eskom’s future involvement in PBMR (Pty) Limited will be as a shareholder, once the conditions precedent to the signed shareholders’ agreement between itself, British Nuclear Fuels Limited, and the Industrial Development Corporation of South Africa have been fulfilled. Eskom will be the host of the demonstration power plant at its nuclear site at Koeberg in the Western Cape, should the environmental impact assessment and the nuclear licensing processes be successful.Eskom, through the Generation Division, is managing these processes, and is carrying out the associated assessments and reviews of PBMR design and safety analyses prior to submitting its reports and safety case to the relevant authorities.
Although some detail design still needs to be done, plant design has progressed to the point where long-lead materials and hardware have been ordered for the core structures and the core barrel. The supply contract for the main helium circuit pressure boundary was placed in December 2005 and that for the turbo-machinery is expected to be placed in the second half of 2006.
Orders for two test facilities to perform heat transfer tests, at high-pressure
and high-temperature, to verify and validate thermo-hydraulic calculations
and analyses, were placed in late 2005.
A contract for a helium test facility was placed in November 2004. This
facility will enable tests of the critical components of the reactivity
control system, reserve shutdown system and the fuel handling system, such
as valves and measuring equipment, in helium at operating conditions. Final
completion of commissioning of the facility at Pelindaba is planned for
the second half of 2006.
| The PBMR project is one of the
most technologically advanced capital investment projects undertaken
in South Africa since 1994. The successful deployment of this leading
technology has the potential to make a significant contribution to local
and international energy supply. In addition, it will contribute to
the transformation of South Africa’s current resource-based economy
to a more knowledge-based economy.
Environmental impact assessments have been conducted for the project, both for the demonstration power and pilot fuel plant. As far as the demonstration plant was concerned, the original design by PBMR was for a 302MW(t) PBMR plant. An environmental impact assessment for this plant commenced in 1999 when Eskom appointed a consortium of independent consultants. An extensive scoping and specialist study programme was undertaken, including comprehensive public participation through numerous interactions (focus group meetings, open days and public meetings), with periods for comment being provided during the scoping and environmental impact assessment phases. This culminated in the submission of the final environmental impact report to the Department of Environmental Affairs and Tourism (DEAT) in October 2002. The evaluation of the final report by DEAT and an International Review Panel appointed by DEAT was undertaken, leading to the issuing of a positive record of decision by the department’s Director-General (DG) in June 2003. Appeals against the record of decision were submitted to the DEAT minister during July and August 2003. An application was brought before the Cape High Court on behalf of Earthlife Africa (Cape Town) in September 2003 to have the record of decision reviewed and set aside. The court judgement was handed down in January 2005. In this judgement the Cape High Court ruled in favour of the applicant, set aside the record of decision, and required the DEAT “to afford the applicant and other interested parties an opportunity of addressing further written submissions to him along the lines as set out in this judgment and within such period as he may determine and to consider such submissions before making a decision anew on the second respondent’s application.” Since the completion of this environmental impact assessments, the decision was taken by PBMR to increase the power output of the plant from 302MW(t) to 400MW(t). This change in output requires that aspects of the assessment and public participation process be repeated, but for the sake of prudence, the parties agreed that a reapplication would be made and the assessment re-run. However, much of the information generated during the previous assessment and recorded in the resultant environmental impact report is still valid in the context of the 400MW(t) demonstration plant. The new application for this project was submitted in August 2005.
During the scoping phase of the technical aspects of the 302MW(t)
and 400MW(t) plant were compared. The existing specialist studies
were evaluated for completeness in view of changed input data, and
the relevant impacts will be reassessed during the environmental impact
assessment phase. During the reporting period, the final scoping report
was issued for public and authority review and the plan of study for
the environmental impact assessment submitted for approval. It is
expected that risk will be completed during 2006. |