Skip Ribbon Commands
Skip to main content
Skip Navigation LinksHome>Media Room>Eskom stops loadshedding for today, but the risk of Stage 2 rotational loadshedding remains high for tomorrow
Eskom stops loadshedding for today, but the risk of Stage 2 rotational loadshedding remains high for tomorrow
Saturday, 01 December 2018: Loadshedding was terminated at 21:16 on 01 December 2018. Due to the high unavailability of plant today, we have been unable to build the necessary reserves thereby resulting in a high probability of Stage 2 rotational loadshedding from 10:00 until 22:00 tomorrow.
 
Generation plant continues to be out on planned maintenance (approximately 5000 MW) and there is a higher than expected number of units (currently at approximately 10000 MW) on unplanned maintenance due to technical faults. Cahora Bassa hydropower plant is still supplying 700 MW less to the grid as a result of a damaged transmission line, which occurred late on Wednesday. Over and above these challenges, we are experiencing low diesel reserves due to the continued pressure on the national grid resulting in excessive usage of open-cycle gas turbines (OCGTs).  In addition, the need to build emergency water and diesel resources to limit the loadshedding possibility or magnitude thereof in the following week also remains. 
 
Our maintenance teams continue to work through the night to bring back units.
 
Customers should note that some municipalities may take longer to restore load. If customers experience outages for longer periods than announced, please contact your supplier (Eskom or the Municipality) as this may be a localised power outage.
 
Eskom would like to thank its customers for using electricity sparingly and industrial customers for their participation in load curtailment today. We will keep customers informed if there are any changes to the system.
 
We sincerely apologise for the inconvenience to affected customers.
 
 