Ingula scheme integration
Page Content
Ingula high-voltage yard: The HV Yard is planned to be energized during December 2013 and thereafter the XLPE cable will be installed and energized during next year. Presently cabling work is in progress on gen transformer bays 1 and 2. |
 Ingula Substation
|
Ingula-Venus 94km line: Ninety one kilometres of conductor have been strung. There is a planned outage for end of October 2013 to connect and commission the loop-out line to the Ingula Venus Line. Work in progress is rehabilitation and finalizing minor works. The final commissioning is planned for end of November 2013. |