History of the Rand and Orange Free State Undertaking

Although the Rand and Orange Free State Undertaking only came into being officially in 1948, it can through its predecessor, the Victoria Falls and Transvaal Power Company, trace its history back to the very early days of power generation and distribution in South Africa.

As in the case of many other industries, the spark which was really responsible for the development of the electricity industry in South Africa was the discovery of gold on the Witwatersrand in 1886.

Initially mining was of the open cast type and the only power required by the mines was some form of prime mover to drive the stamp mills which constituted the reduction plants of the period. With the discovery of the cyanide process which enabled the pyritic ore found at greater depths to be treated satisfactorily, a complete change in mining operations and electric power requirements took place.

The gold mines themselves provided their own power requirements, but it was not long before most of these installations became inadequate to meet the expanding requirements of the mines, and firstly the Rand Central Electric Works and the General Electric Power Company Limited was established to help provide the power requirements of the mining industry.

In 1906 the Victoria Falls and Transvaal Power Company was formed with the object of generating power at the Victoria Falls and supplying it over a distance of some 1 000 km to consumers on the Witwatersrand, and although a small power station was in fact established, the remainder of the dream was not fulfilled. 1907 the Victoria Falls and Transvaal Power Company took over the Rand Central Electric Works and the General Electric Power Company and became responsible for the provision of electric power along the Witwatersrand to the mines and municipalities.

As a result of considerable German influence both on the Rand Central Electric Works and initially on the Victoria Falls and Transvaal Power Company, the transmission and distribution voltages that were adopted were based on those in use in Germany at the time, and accordingly a 42kV transmission system was first constructed from Brakpan to Bantjes (Florida) looping into a distribution station at Hercules (Boksburg), the power stations at Simmerpan and Rosherville and a distribution-cum-air compressor station at Robinson(Johannesburg) en route.

With the establishment of the Vereeniging power station in 1912, two double circuit 88kV lines were built from Vereeniging to Robinson, and it is interesting to note that these latter two lines modified to single circuit, are still in operation as well as considerable sections of the original main 42kV east-west system, and certain 21 kV and 10,5 kV networks fed from the original power stations and distribution stations.

With the mines being established virtually in a straight line along the Witwatersrand, the initial load centre comprised a narrow strip some five to eight kilometres broad and some 100 kilometres long and this formed the basis for the Rand Licence Area granted to the Victoria Falls and Transvaal Power Company in 1910 by His Excellency and Governor-General under the Power Act of the Transvaal.

This licenced area of supply was extended from time to time under the above Act and subsequently under the Electricity Acts of 1922 and 1958 and finally comprised a fairly narrow strip on each side of the Witwatersrand, extending from Nigel to Randfontein together with a circular area approximately 5 kilometres around a radius around Heidelberg, and a further small area centred around Vereeniging.

After the industrial unrest at the start of the 1920’s which culminated in the 1922 strike, a period of industrial tranquillity was entered which led to considerable expansion by the goldmines and other industries and the provision of additional electric power became a matter of urgency.

As a result the Witbank power station was constructed and was linked by means of a double circuit 132 kV transmission line to the Rand system at Brakpan in May 1926. This was the first line of this voltage in the then British Empire and was the source of considerable troubles for the first few years. Joints pulled out conductors broke due to vibration and simultaneous faulting of both lines during storms was common. These difficulties were overcome by substituting compression joints for the originals, the fitting of vibration dampers and the installation of counterpoises, and these modifications together with a rather unorthodox protection system resulted in a high dress of reliability of supply.

By 1930 further reinforcement of the supply to the Reef had been necessary and two further I 84 kV lines had been built from Vereeniging power station to Vlakfontein Distribution Station (near Springs). In view of the difficulties that had been experienced with double line faulting on the Witbank – Brakpan 132 kV double circuit lines, these two new 84 kV lines were built approximately 2,5 kilometres apart to eliminate the likelihood of both lines being struck by the same lightning flash. Due to the higher loads being required by the fewer consumers’ a start had by this date also been made in supplying consumers’ substations at 42 kV, and at the same time larger transformers of higher impedance, i.e. 2500 kVA and 4.3% impedance were bring installed at these substations.

The period 1930-1940 led to a considerable expansion on the Victoria Falls and Transvaal Power Company. New mines were being opened in the Springs–Nigel area, in the Venterspost – Blyvooruitzicht area and also in the Klerksdorp area. The latter two areas were well outside the area of supply granted under the original Rand Licence and its subsequent amendments, and as a result a new licence known as the Rand Extension Licence was applied for and was granted by the Electricity Control Board in May 1934. This licence, which has been amended from time to time gave the Victoria Falls and Transvaal Power Company a considerably increased area of supply and enabled both the Venterspost – Blyvooruitzicht – West Driefontein mining area and the Klerksdorp area to be developed.

As the initial loads in this latter area were small, i.e. there were only three consumers each requiring only approximately 1000 – 2000 kW, the capital cost of providing supply was of paramount importance if the scheme was to be economically justifiable and accordingly a single 84 kV line was constructed, using the minimum size of copper conductor compatible with corona requirements, i.e. 70 sq.mm.

Spurs were constructed from this main line to each point of supply where one or more 1500 kVA or 2500 kVA transformers were installed and in spite of the line being over 160 kilometres in length, a very high reliability of supply factor was achieved.

It is interesting to compare these early beginnings with the present day picture where two 400 kV lines were now under construction to feed two 500 MVA 400/132 kV and two 180 MVA 132/88 kV transformers to provide an adequate supply of electricity to the Klerksdorp area itself and the areas west and north-west.

Coincident with this expansion to the west of the Witwatersrand additional loads were appearing along the Witwatersrand itself and with the establishment of Klip power station a few kilometres north of Vereeniging, additional reinforcement of the “fan” system of 84 kV lines to the Witwatersrand area were provided.

1939 saw the outbreak of the Second World War and the need to supply power to maintain the current gold output and also for the various industries that were established, were the number one priority of the period.

With this latter development particularly, power lines had to be built and in conjunction with a local manufacturing firm, a hexagonal steel pole was developed and fabricated, this proving to be a very satisfactory substitute for the tubular steel poles which up to that time had been imported.

The local manufacture of line hardware was started and as copper conductors were being drawn and stranded locally and had been in use for some years, the only item which had to be imported were insulators.

Over the war years the increase in electrical load was relatively small, but with the advent of peace there was a considerable demand for additional power, not only from the gold mining industry which was about to open up the Free State Gold Fields and expand the development of the Far West Rand and Klerksdorp areas, but also for municipalities and industries which, due to the restrictions on imports imposed during the war, had sprung up and were now wishing to expand and bring about the greater industrialisation of the country.

In the immediate post war years arrangements had been made to supply a cement works near Hennenman, Orange Free State, by an 88 kV line from the Vaal power station just over the river from Vereeniging and which had been commissioned in 1945.

Fortunately Hennenman is on the eastern fringe of the Orange Free State Gold fields and as the construction of the line coincided with the request for power for preliminary work on the gold fields, it was an easy matter to extend this line and later follow it with another. As in the case of the Klerksdorp area, the initial method of supply was by building spurs from the 88 kV lines to step-down substations on the mines, but even as this was being done, planning was progressing for 88/42 kV distribution stations and local 42 kV networks to supply the mines.

In retrospect this was possibly not the right decision to make bring based on information that turned out to be far from accurate. Assurances were obtained that the Orange Free State Gold Fields’ demand for power could never exceed 150 MW nor would mines be established south of the Sand River. Today the hourly maximum demand of the gold fields which stretch from Virginia in the south, to Allanridge (Loraine Goldmine) some 25 km north of Welkom, including the municipalities which have grown with the mines, totals some 530 MW, and needless to say there are also mines south of the Sand River.

With the need to supply the Orange Free State Gold Mines in particular, as well as the Rustenburg and Lichtenburg areas where development was also taking place, it was again necessary to extend the licenced area of supply and to meet this expansion, the Greater Rand Extension Licence was granted in 1947, which extended the area of supply to the north, west and south of the area covered by the Rand Extension Licence.

As additional requests for power had been received, this Greater Rand Extension licence had been modified from time to time and the latest application that was made would, give the Undertaking a supply area stretching from Beit Bridge in the north to beyond Wepener in the south and from near Delmas in the east to the Botswana border in the west.

As stated elsewhere, as a result of the Electricity Act of 1922 and the formation of the Commission in 1923, the Commission had the right under the Act to take over the Victoria Falls power system in 1950. In actual fact, however, it was negotiated that the take-over would take place in 1948 and from this date the Victoria Falls system became the Commission’s “Rand Undertaking”, this title being subsequently altered to Rand and Orange Free State Undertaking.

It was realised from the foregoing that until the1950’s, the gold mining industry had by far been the major consumer of the Victoria Falls and Transvaal Power Company and the Rand and Orange Free State Undertaking.

This was borne out by the fact that in 1939 the units sold to the gold mining industry represented 88 kV of the total units sold, while by 1950, in spite of the interim growth and supplies to additional municipalities and industries, this percentage was still as high as 75%.

As a result of this there had always been very close contact between the gold mining industry and the Undertaking, and no better example of this close contact can be given than that which was experienced in the early 1950’s when, in the immediate post war period, major expansion was taking place in both the mining and industrial spheres, but at the same time considerable difficulties were being experienced in obtaining new generating plant.

In order to achieve maximum availability of generating plant the period between overhauls were extended as much as possible without endangering reliability of supply, and special maintenance procedures were instituted to reduce outage times to the minimum.

Obviously the first efforts by the Mining Industry towards optimum utilisation of the power that was available were directed towards and improvement in load factor. In 1949 the weekday load factor of the mines was of the order of 78% and by making use of the daily and weekend valleys by shifting pumping rock hoisting to off-peak periods, and improvement in the weekday load factors to close to 88% was achieved and it is interesting to note that these particularly high load factors had shown very little increase in succeeding years, particularly in the case of the larger mines.

Working on the principle, which is still adhered to, that wherever possible, applications for power are dealt with in the order in which they are received, as screening committees were formed on the Undertaking towards the end of 1950, the function of this groups of senior officials being that of limiting the supplies drawn from the system so that the total load should not exceed the generating capacity available.

The basic pattern of the restrictive measures was built on the fact previously mentioned that the Mining Industry consumer 75% of the output and as additional power became available, this basic ratio of 75:25 was maintained as far as possible, the succeeding priorities being as follows:

  1. Essential services operated by Government, Provincial Local Authorities and Public Utilities.
  2. Industries providing essential supplies for the Mining Industry or for essential services.
  3. Industries manufacturing commodities essential to the national economy.
  4. Applications which could not be founded on essentiality were accorded such priority as could be supported by considerations of national interest.
  5. Housing being a national problem, some priority was given to expansion of residential townships and rural reticulation systems within or contiguous to existing reticulated areas.

The allocation of 75% of the available sent out capacity was in the nature of a bulk allocation to all mines under the control of the Transvaal and Orange Free State Chamber of Mines, in turn were responsible for the allocation to individual mining consumers based on the availability of power and the needs of the mine.

With the generating stations running with no spinning reserve at all, it was obvious that provision had to be made for unforeseen loss of plant and in view of the fact that the mining industry were the major consumers, the appointment of Power Control Officers at each mine and the fact that in the case of the majority of other consumers, load shedding procedures were somewhat complicated due to the time taken for effective communication and the question of prompt response, it became the lot of the Mining Industry and a few large industrial consumers to bear the brunt of load reductions which became necessary due to loss of plant.

Targets A,B, and C were set to cover the loss of one, two or three 30 MW generators and the Chamber of Mines then calculated reductions for each mine targeting consumer in accordance with the above targets. If, in the opinion of the Undertaking’s Control Engineer, a reduction in load was necessary for any reason, the reduction in terms of the predetermined targets was passed to the Distribution Officials who were responsible for ensuring that the instruction was received by the appropriate official on each mine.

It is interesting to note that during the period 1950-1955, load reductions took place as follows:

Year Occasions
1950
97
1951
143
1952
204
1953
75
1954
26
1955
2

The longest restriction imposed was six hours, eighteen minutes, the average duration being of the order of two and a half to three hours. The response when load shedding became necessary was excellent and was generally achieved with 15 minutes of loss of generating plant on peak, but frequently it was possible to anticipate excessive loads and impose the necessary target restrictions in advance.

As a result of this shortage of generating plant to cater for the post war expansion, either new projects or expansion of existing businesses were delayed, but it was possible to give realistic dates for commencement of power supplies and thus applicants were able to defer capital expenditure and other commitments accordingly.

Total units showed an overall increase of 54% during the period 1950-1955, but though this was a considerable achievement in view of the shortage of plant, it must be borne in mind that the period was also utilised to the full for the opening up and development of a number of new mines which were brought into production after the restrictions were lifted after the winter in 1955.

Although there were these restrictions in the use of power, the development of the Undertaking continued and with the expansion of the Orange Free State and Klerksdorp Mines, the construction of the Vierfontein power station provided welcome reinforcement to the supply networks to these two areas.

Because of the relative distances and loads involved, the power station was planned for dual transmission voltages, 132 kV for the supply south to the Orange Free State mining area and 88kV for the Klerksdorp area and the establishment of the mines in the Stilfontein area, that it became a more economic proposition to supply this load at 132 kV to a 132/88kV distribution station (Carrdell), than to multiply the number of 88 kV lines, and it also provided a base which to supply the Lichtenburg area at 132 kV to replace the 88 kV supply to the area from the West Wits station.

The early 1950’s also saw the establishment of the Rural Electrification Department of the Undertaking. Up to that time very little rural electrification had been undertaken, what little development there had been in the embryo Sandton and Randburg Municipalities of today being carried out by the Germiston and Georgetown Lighting Department; this Department also being responsible for the urban reticulation within the Germiston Municipality.

With the takeover of this responsibility by the Municipality themselves in 1951 and an approach by a number of farmers in an area midway between Alberton and Heidelberg regarding the possibility of a supply of electricity, the Rural Electrification Department was established on the 1st December 1951, to provide supplies to all small consumers outside municipal supply areas.

At that stage they were unaware that the then rural areas immediately north of Johannesburg would develop into the vast municipal complexes of Sandton and Randburg which, with their tremendously rapid development, together with that of the other areas contiguous to Johannesburg and the adjacent Reef municipalities had hampered to some extent the provision of supply to the more distant rural areas.

With the further development of particularly the mining industry due partly to new uranium production, the establishment of further generating stations became necessary and coincidently the Taaibos and Wilge stations were constructed over this period 1954-1958.

While the output of Wilge situated some 20 kilometres east of Witbank fed into the eastern sector of the system by means of a loop of the Witbank Stepdown 132 kV lines, Taaibos, situated some 18 kilometres south of Vaal power station on the Clydesdale Colliery, was used mainly to reinforce the supply into the Far West Rand area where the loads of the newer mines such as Doornfontein and West Driefontein, were starting to assume considerable proportions and were resulting in the capacity of the original 88 kV transmission becoming inadequate.

Initially four 132 kV lines were built from Taaibos into the Far West Rand each terminating on a 90 MVA 132/42 kV transformer at distribution stations strategically situated in relation to the load, this being followed later by the construction of two additional 132 kV lines from Taaibos and the provision of 132 kV busbars at the distribution stations together with 132 kV switchgear on the stepdown transformers and 132 kV interconnectors between the distribution stations.

When the large power requirements of Western Deep Levels became known it was decided rather than supply the loads at 42 kV from the nearby distribution stations, to incorporate the substations in the established 132 kV network and to step down directly to the consumer’s voltages, i.e.11 kV and 6,6 kV.

It should also be noted that the introduction of a 312 kV network into this Far West Rand area provided a convenient point for the initial 132 kV transmission to the Rustenburg area in 1959, which initially had been supplied by means of a light 88 kV line from the West Wits Distribution Station, but which because of the increase in platinum loads in the area, was becoming inadequate.

While the 1950’s were marked by curbs on development imposed particularly by the shortage of generating capacity, the 1960’s heralded in a period of widespread development in all sectors.

The impetus of the expanding economy was already being felt in the latter years of the 1950’s but expansion had been generally limited to a few particular areas, e.g. the OFS and Klerksdorp gold fields, but the 1960-1970 period saw the Undertaking develop in all directions.

A historic year in the growth of the Undertaking was 1961 when the maximum hourly demand in reaching 2016 MW, topped the 2000 MW mark for the first time, the figure of 4000 MW having been exceeded in 1972 for the first time, an average rate of growth over these last eleven years of approximately 6.5% which, in view of the closure of a number of gold mines on the Far East Rand in the last few years, was considered as very satisfactory.

The load growth of the OFS Gold fields had, towards the end of the 1950’s, indicated that the 132 kV transmission already provided would soon be both inadequate and uneconomic and with the establishment of Highveld power station built adjacent to Taaibos, it was decided to build two 275 kV lines from Highveld to a new distribution station to be known as Everest which was to be connected at 132 kV to the already established distribution stations around the gold fields, i.e. Virginia, Alma and Grootkop, these lines being commissioned during 1959, and were the first transmission lines of this voltage in South Africa.

Following requests for power from a number of municipalities in the south-eastern Free State, considerable expansion in this area took place. The already established Virginia – Senekal 88 kV line was extended in 1960 to provide supply to the municipalities of Marquard, Clocolan and Ficksburg, while in 1961 this was followed up by the provision of supply to Bultfontein, Excelsior, Tweespruit, Wepener, Dewetsdorp and Edenville, with Thaba’Nchu following in January, 1962. It is interesting to note that in 1948 when the first power line was built to the OFS Gold Fields, Parys was the only municipality in the Orange Free State Undertaking and that by early 1962, a total of 31 local authorities in that province obtained their electric power requirements from this Undertaking, this number having increased by the end of 1972, to 40.

With construction of the Carrdell – Watershed (Lichtenburg) 132kV line network in the area which was supplying the White’s and Pretoria Portland Cement companies at Lichtenburg and Slurry respectively, together with the municipalities to Lichtenburg, Mafeking, Zeerust, Coligny and Venersdorp.

Following successful negotiations, a new 88 kV line some 190 kilometres in length was built in 1962 to supply the municipalities of Sannieshof, Delareyville and Vryburg. In addition in 1962, Bloemhof Municipality obtained a supply from the Undertaking from a 60 kilometre extension to the existing 88 kV line supplying Wolmaransstad and later in 1965 a further extension from Wolmaransstad was constructed for supply to Schweizer Reneke.

To the east, expansion was also in progress with the construction in 1964 and 1965 of some 250 kilometres of 88 kV line to supply the South African Railways Union – Volksrust electrification scheme which enabled the Undertaking to supply the municipalities of Greylingstad and Standerton, the latter municipality, although in the Undertaking’s area of supply, having previously obtained their electricity requirements from the Eastern Transvaal Undertaking.

Along the Witwatersrand itself considerable expansion was taking place both with regard to municipal and industrial load, and in the latter field, new or additional large supplies were given to African Explosives for their new Nitrogen Plant, to SA Pulp and Paper for their new Enstra Mill and to Electrolytic Metals and Palmietfontein Chrome, Iscor Vanderbijlpark, Amcor, Dunswart, Scaw Metals, Union Steel, to mention a few, together with numerous smaller industrial supplies.

Obviously with the growth that was taking place, considerable reinforcement was required to meet the loads that were increasing so rapidly in most areas, and with the commissioning of Komati power station some 36 kilometres south of Middelburg at the beginning of 1962, the start of a 275 kV backbone for the Undertaking was commenced that was to stretch from Komati via Nevis (near Springs) for supply to the Far East Rand complex, Snowdon (west of Heidelberg) for supply to the near East Rand complex, Highveld and Everest (between Welkom and Virginia) for supply to the OFS Goldfields by the end of 1962. An extension to this backbone via two 275 kV lines Highveld – Scafell was completed in 1963 to reinforce supply from Scafell to the Far West Rand area, where the load particularly of the goldmines was increasing rapidly with the development of Western Deep Levels.

Seven new traction stations in the Undertaking’s area of supply were equipped and commissioned for the Klerksdorp – Kimberley electrification towards the end of 1964,and four further stations to serve the new rail link between Houtkop and Potchefstroom and some 94 kilometres 88 kV line were commissioned early in 1965.

The decision to construct a major 400 kV transmission system from the power stations situated in the Eastern Transvaal Coalfields to the Cape with major distribution stations at selected points along its route provided the Undertaking with two convenient additional input to cater for its growth of load.

The first was to be Atlas Distribution Station situated near the Vaal Dam and very close to the route of Snowdon – Highveld 275 kV lines so that by looping these lines into Atlas and the completion of three Camden – Atlas 400 kV lines in 1967, gave considerable reinforcement to the supplies fed from Snowdon and also from Highveld. It should be noted that the 720 MVA 400/275 kV transformers installed at Atlas were the largest transformers by far, in the country at that time.

With the loads being notified for new fold mining consumers in the Far West Rand such as kloof, Elsburg and East Driefontein and in addition, the platinum mining loads in the Rustenburg area, it became very apparent that the 132 kV transmission to the Far West Rand area from Sarfell was becoming inadequate and accordingly with the major input point at Atlas available, it was planned to build two 275 kV lines to a new distribution station to be known as Bernina, in the Far West Rand area and the Bernina Distribution Station was commissioned in April, 1969.

Coincident with this work the 400 kV system was being extended further southwards towards the second major 400/275 kV distribution station on its route to be known as Perseus. This station is near Dealesville in the Orange Free State and was commissioned in 1969, and by means of looping into it the Everest – Kimberley 275 kV line, Perseus is able both to supply to the OFS gold mining area (via Everest) and also to the Cape Northern Undertaking at Kimberley.

While this major expansion and reinforcement in the Eastern, Western and southern sectors was taking place, the northern areas were also awakening.

Following a tentative enquiry regarding the possibility of providing supply from Warmbad, it was felt that this was likely to be the forerunner of major development in the Northern Transvaal and accordingly it was planned that a 275 kV line should be constructed from Esselen Distribution Station to Warmbad, work commenced on this project in 1965.

This 275 kV line was initially operated at 88 kV and supply furnished to Warmbad in May 1966, and was operated in this manner from some 21 months. In the meantime, as hoped, negotiations had been completed with Pietersburg Municipality for a supply at Potgietersrus, which Pietersburg were supplying and in February 1968, the Esselen – Warmbad line was converted to 132 kV operation, the 132 kV substation at Warmbad commissioned together with the Warmbad – Potgietersrus 132 kV line from which a temporary supply at the latter point was made available.

The development was not by any means complete in this area and even as the above supplies were being given, the 132 kV line to Potgietersrus was being extended via Pietersburg to Louis Trichardt, a distance of some 110 kilometres and supply to this municipality was furnished towards the end of 1968.

Following the application by a large number of farmers in the Brits District for supply, the 88 kV system was also extended north to provide a convenient step-down station near Brits to supply their needs and following this development, a new supply to the Brits Municipality which had previously been furnished by the Pretoria Municipality, was made available. These developments in this particular area have resulted in a very large and successful rural scheme and some 1 300 rural consumers were not supplied in this particular area.

In the north-west too, large scale development was in progress. The platinum market was extremely buoyant and the established Rustenburg Platinum mines was expanding, while Impala Platinum and Western Platinum Mines were commencing operations. To meet these large load increases a second Doornfontein – Trident 132 kV line was constructed and completed in January 1969, to provide a more reliable and safe supply, but this proved inadequate and accordingly further reinforcement was planned, i.e. a 275 kV line from Bernina to a new 275/88kV station (Trident) outside Rustenburg. This 275 kV line and the new station was completed in September 1971, just in time for the platinum market to collapse and loads were curtailed considerably, and a number of other major system extensions in that area were accordingly deferred.

In accordance with the government’s policy of aid to neighbouring countries, very amicable discussions and negotiations were carried out with the Lesotho Electricity Corporation and with the backing of both Government, a supply was made available in April 1968, to Lesotho by means of an 88 kV line from Ladybrand to Maseru, and this was followed in 1970 by a further supply to Lesotho at the border post adjacent to Ficksburg.

As a result of the agreements reached with the municipalities of Johannesburg and Pretoria, the fact that the original 88 kV “fan” lines from the south into the Central Witwatersrand were becoming completely inadequate and a decision to take supply from the Cabora Bassa Hydro-Electric Project in Mozambique was made, a start on the Apollo distribution Station began in 1969.

With the commissioning of the first stage of the Cabora Bassa Project in 1975, the dreams of the pioneers of the Old Victoria Falls and Transvaal Power Company didl in part come true as they had too visualised the transmission of power from the dammed up waters of the Zambesi – though they had their eyes on the Victoria Falls itself as the power source.

Unfortunately due to both steel and cement shortages, it was not possible to commission the first 400 kV line to Apollo from Hendrina Power Station until the middle of 1971, the second line being completed early in 1972.

The above shortages of steel and cement also affected the 275 kV lines between Apollo and Jupiter Distribution Station near the Johannesburg/Germiston boundary, whose commissioning was delayed until January 1972. This latter station now supplied the Germiston area and certain mining loads close by, and early in 1973 was the source for the first major input to Johannesburg and later for supply to the Alberton area.

Apollo would also in the future be the point of supply for the new 400kV system to the Western Transvaal via Pluto Distributon Station where it tied into the present Bernina-Tridant 275 kV line for supply to the platinum mining areas north of Rustenburg and the gold mining areas of the Far West Rand and then to Hermes in the Klerksdorp area to bolster the supply to this gold mining area.

In addition, from Pluto Distribution Station a 275 kV line was envisaged to the Lichtenburg area to reinforce the supply to the cement procedures and other consumers in that area.

Before leaving the present era, one must make mention of the supplies to Iscor at their Vanderbijlpark steelworks, the 132/33 kV supply to their combination mill made available in 1970, together, in the same year, with the 275/33 kV supply via two 90 MVA transformers at the Olympus substation for supply to their two new 60 MVA are furnaces; the supply to the National Petroleum Refinery at Sasolburg also in 1970, via two 25 MVA 88/33kV transformers; the African Explosives Midland Factory also at Sasolburg; the African Explosives Midland factory also at Sasolburg; the electrification of the railway line Kroonstad – Harrismith in 1971, as also the start on the Pretoria North – De Wildt section in 1971 and 1972; new supplies to various municipalities such as Benoni, Vanderbijlpark, Parys during 1971, to cater for their increase load growth with initial partial bulk supplies to Pretoria and Bloemfontein, the latter from Perseus Distribution Station during 1972, and the extension of the 132kV line from Louis Trichardt to Messina, to name just a few of the larger projects that have recently been completed.

While all this major work on the main system was in hand, the Rural Electrification Department was building up a considerable organisation to cater for the rural and urban development that was occurring.

Due to shortage of capital in the early 1950’s this expansion was at a fairly slow rate and initially work was restricted to extensions to the areas where reticulation circuits had already been started, e.g. Lombardy East, Buccleuch, Morningside, Sandown, Sandhurst and Ferndale together with a small area south of Germiston.

With capital becoming more freely available the tempo of reticulation development was increased and with the rapid development of large townships north of Johannesburg, the resources of the Department were hard pressed to keep pace, but this to a large extent was achieved and in addition supplies were provided to the areas east, west and south of Johannesburg, e.g. Halfwayhouse, Walkerville, Henley-on-Klip, Boschkop/Muldersdrift, Magaliesburg and Brentwood Park.

As the main development in these areas were completed, it was possible to move further afield and today the Rural networks extend from the Balfour/Grootvlei area in the east to the Lichtenburg/Sannieshof area in the west and from the Brits/Northam areas in the north to the Tweespruit/Westminster area in the South.

When one remembers that the total load supplied by this Department in December 1951, when it started its life, was 6 MW and the number of consumers were 1 300, the present load of some 179 MW and some 29 000 consumers represented a considerable and meritorious achievement, particularly as during the latter years quite considerable areas and a large number of consumers had been taken over by various municipalities as their boundaries had been extended.

And now, what of the future! Naturally the long term was extremely difficult to predict, but in the short term the continued expansion of the Undertaking appears to be assured.

While no dramatic upsurge in the loads of the gold mines were expected even as a result of the free market price of gold, the present price appeared adequate to ensure a lengthening in the life of most mines, some only by possibly a year or two, others by a considerable period of a number of what were previously dying mines, resulted in a greater overall load growth over the next few years. With a major increase in the official price of gold, however, a number of new mines would almost certainly start up.

With platinum apparently the most suitable catalyst for exhaust converters for the American motor car industry at this stage, a considerable increase in the load of the platinum mining industry at least for a few years, appears certain and should the European and Japanese governments follow the example of the Americans in legislating against motor vehicle pollution, an unprecedented expansion and consequently growth in the electrical load could occur in this particular industry.

The South African Railways too were embarking on a large electrification programme with the doubling of the number of traction stations between Kimberley and Volksrust, the electrification of the section Kroonstad – Bloemfontein together with the provision of additional traction stations along the reef.

Industrially too, the Undertaking appears well set for the future. Two large 50 MVA furnaces were due for commissioning at African Metals (Kookfontein) towards the end of 1973, with Scaw Metals following in 1974 with a 30 MVA unit. Iscor’s Northern Complex at Vanderbijlpark required their initial supply in 1973, and African Explosives’ new Nitrogen plant at Modderfontein (40 MW) was due to come online early in 1974.

With the above and continued growth expected both from the municipal consumers and also from the continuous Rural development, it would appear that the Undertaking was set fair to continue on the road of expansion on the sound foundations provided in the past.