Embedded generation application process


Cost to be grid-tied:
The embedded generation application process starts with your submission form to Eskom to connect your installation to the national grid. We will then issue a quote, outlining the cost for your grid-tied connection.
The connection charges include:
• A quotation fee
• Metering changes
• Any network upgrades that may be required
We will only initiate the work to authorise the connection once the quote has been accepted, the charges paid, and the relevant agreements signed.
Possible agreements to be signed:
- A new Eskom electricity supply agreement if the existing agreement is old, if there is a tariff conversion, or changes to the supply.
- Amendments to the electricity supply agreement to activate energy offset, wheeling, or banking.
- A connection and use-of-system agreement stipulating the conditions and obligations for the generator connection.