Six coal-fired power stations performing at 70% EAF for the first time since 8 May 2022 March 16, 2023March 16, 2023
Eskom’s placement on CreditWatch Positive by S&P Global is a positive development which endorses the positive impact of the Debt Relief on Eskom’s financial position and overall liquidity. March 16, 2023March 16, 2023
Stage 4 loadshedding will be implemented from 16:00 today until 16:00 on Monday. Thereafter, Stage 5 loadshedding will be implemented until 05:00 on Tuesday March 12, 2023March 12, 2023
Loadshedding will be reduced from Stage 4 to Stage 3 over the weekend with Stage 1 loadshedding forecasted for Sunday morning March 10, 2023March 10, 2023
Stage 4 and 5 loadshedding will continue to be implemented throughout the week March 6, 2023March 6, 2023
Stage 4 loadshedding will be implemented from 16:00 today until Tuesday morning March 5, 2023March 5, 2023
Loadshedding will continue to be implemented at Stage 4 until 16:00 today. Thereafter, Stage 5 loadshedding will be implemented from 16:00 today until 05:00 on Friday. Stage 4 loadshedding will again be implemented from 05:00 on Friday until 05:00 on Saturday. March 2, 2023March 2, 2023
Loadshedding will continue to be implemented at Stage 3 until 16:00 today. Thereafter, Stage 4 loadshedding will be implemented from 16:00 today until 16:00 tomorrow and Stage 5 loadshedding will then be implemented from 16:00 until 05:00 on Thursday. February 28, 2023February 28, 2023
Sikonathi Mantshantsha leaves Eskom at the end of his three-year fixed-term contract February 27, 2023March 3, 2023
Loadshedding will be gradually reduced to Stage 3 during the course of the week. February 26, 2023February 28, 2023