Varying stages of loadshedding will be implemented until midnight on Sunday

Thursday, 27 October 2022: Stage 3 loadshedding is currently underway until 16:00 on Thursday, thereafter, it will increase to Stage 4 until 05:00 on Friday morning. Loadshedding will be lowered to Stage 2 at 05:00 – 16:00 on Friday. It is anticipated Stages 2 and 1 loadshedding will be implemented during the weekend.

The emergency generation reserves are almost depleted, both the diesel and pumped storage dam levels. These, together with persistent high levels of breakdowns of generating units, are among the major contributors to the continuing generation capacity shortages.

Eskom will publish a further update as soon as any significant changes occur.

Since Tuesday evening Eskom teams have returned a generating unit each at Duvha, Kendal and Medupi power stations to service.

We currently have 5 683MW on planned maintenance, while another 16 585MW of capacity is unavailable due to breakdowns.

Loadshedding is implemented only as a last resort in view of the shortage of generation capacity and the need to attend to breakdowns.